It is an easy to use application with an Excel like user interface. And it is lightning fast; can export and import thousands of records in seconds.
PRMTransfer uses Primavera P6 credentials .We use Primavera P6 login information to logon the PRMTransfer tool.
![](/images/2019-11-12_13_16_27-PRMTransfer_-_PRM_Yazilim.png)
After login use the PRM logo button to access options.
![](/images/PRMTransfer_-_1.png)
In the options panel under Project>Resource Assignment tab you can add desired columns to display.
![](/images/PRMTransfer_-_2.png)
Add Planned Units column and any other columns you need to the right panel to display.
![](/images/PRMTransfer_-_3.png)
After clicking "Ok" select your Project from Project Data tab.
![](/images/PRMTransfer_-_4.png)
After selecting your project click "Activity Resource Assignments" button to get data from Primavera P6.
![](/images/PRMTransfer_-_5a.png)
The data you get can be saved as an excel worksheet from options and "Save".
![](/images/PRMTransfer_-_5c.png)
![](/images/PRMTransfer_-_5b.png)
After getting data from the Primavera P6 you can update the activity data as your preference.
![](/images/PRMTransfer_-_6a.png)
For example; change the planned units value of the activity to the required value. As in the example we change from 252 to 260.
![](/images/PRMTransfer_-_7a.png)
After changing the value click "Send to P6" from upper left menu and confirm the result of successful transfer.
![](/images/PRMTransfer_-_8.png)
You can see the changes in Primavera P6 after refreshing the Primavera P6 application with "F5".
![](/images/PRMTransfer_-_9.png)